Thursday, June 5, 2008

1 down, 3 to go


The restoration crew finished the North side of the necessary house at Smiths Fort plantation on June 5th, 2008, leaving the South side, plus the tool shed on the other corner of the yard to go. The shingles are 24 inch, medium cedar "handsplits", meaning they are about one-half inch at the butt, sawn on the bottom and split on the top. The process of setting up scaffold, tearing off the old roof and installing new shingles takes two men about two days per side, which does not include trueing the shingle edges and rounding them on a bandsaw. The old shingles were sawn cypress and had been installed @1985.