Thursday, May 12, 2011

The Beast is Caged

The Restoration Department has finished installing the six-foot tall picket fence around the new HVAC unit in the back yard of The John Marshall House. The crew used several techniques and tools to build the fence efficiently. When the fence rails were set, they were hung at a very precise height from grade. The pickets were all cut in the shop with a chop saw, so they were exactly the same length. The crew could then set the picket bottoms flush with the bottom rail, and the picket tops would come out dead even. The frame was set on site and painted in a day. The 174 pickets were primed and painted off-site with an airless sprayer, in a day and a half. The crew used a cordless nailer, loaded with two-inch stainless steel nails, to attach the pickets, also in a day and a half. Slightly over 1000 nails were used on the pickets.