Wednesday, July 23, 2008

Smith's Fort Facelift et al







The restoration crew is deligently trying to diminish the deferred maintenance list before August 11th when they start the siding phase at the Hollow. They fixed the leak over Betty's head at the Cole-Digges on July 1st, which turned out to be a very poorly sealed flange for an air duct in the HVAC unit. Betty was so impressed with the aroma of the Geocel 2315 liquid rubber product we used that she is trying to find it in aerosol form to spritz in her office. The pictures you see are the exterior elements of Smith's Fort. It is our intention to repaint all of the exterior trim of the house. As you can see, it needed doing. Due to the weather and the extensive amount of scraping, sanding and window reglazing this job will take 3 men about 4 weeks to finish.


No comments: